Hi

We have strategy 40 in R/3 and 20 in APO. When we load PIR with VSF in R/3 , the forecast is allocated to STO PO and all other requirments in APO. We would like to use LSF in R/3 but the allocation in APO should happen only to SO , which is not happening now. Is there any setting missing?

Prasanna

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi

Can you pl explain little bit more.

michael_thinschmidt
Contributor
0 Kudos

Have checked the checking instructions ? The allocation check needs to be activated of course..