Dear All,

i want to know what is the difference between Availability Check and ATP (Available to Promise)

and is there any role of MRP and Transfer of Requirement in availability check?

pls let me know i am new to SAP

Regards

Tig

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear sap tiger

Your question is very very broad, vague & an entire subject & business model in itself.

I am sure, none of our friends here, can help you with this question of yours.

There are tons of materials online, people have written books,& many such things.

Pls be specific, atleast to a certain extent in Av.check questions.

Just for doing my small part in answering yout question:

there are 3 types of Av check

a) Av ch under product allocation.

b) Available to promise [ATP]

C) Global ATP [Av chk across multiple plants]

Firstly, Av check has to be carried out & then TOR {TRANSFER of requirements} takes place. (whether individual or collective}

Any specific questions, you are most welcome.

Rgds

Sumanth.Gururaj

Consultant/Systems Analyst

SAP SD/MM/CIN

Edited by: SUMANTH GURURAJ on Feb 22, 2011 6:57 PM

Former Member
0 Kudos

Dear Sumanth,

Thank you for ur answer

Regards

Tig

Answers (1)

Answers (1)

Lakshmipathi
Active Contributor
0 Kudos

Welcome to the forum.

Before posting please search the forum whether the question has already been answered. If not, you are welcome to post. The question what you had posted has been answered many times. Please put some efforts to search the forum.

thanks

G. Lakshmipathi

Former Member
0 Kudos

Thank you Sir,

I will follow the guidelines

Regards

Tig