One of my warehouse in Decentralized WM. I have distributed the delivery in VL06I. I want to do PGR in VL32N , but it is in display mode.
I understand that system is expecting a report from EWM about the picking details of delivery. But, without this also, can I directly do PGR in VL32N?
Please advice
regards,
Shashidhar
Hi Shashidhar,
In a DWM scenario the inbound delivery is replicated to your WM system from ERP. In the WM system you must 1st create the TO and do the confirmation and only then can you post the GR from the WM system (idoc to go to ERP system to post the material doc.)
I hope this helps.