Does SRM PPS allow item level technical acceptance of bid?

Former Member
0 Kudos

Hi,

Does SRM PPS allow item level technical acceptance of bid?

Accepted Solutions (0)

Answers (1)

Answers (1)

yeushengteo
Advisor
Advisor
0 Kudos

Hi,

A technical bid response is made in cFolder for a RFx response from a bidder. In other words, an acceptance of a technical bid response is for all items before proceeding to open the RFx price response in SRM. During awarding in SRM, you can select/reject the item at item level.

So in short, you cannot accept technical bid response on the item level.