Changing a date on a Milestone.

Former Member
0 Kudos

Hi All,

How can I ensure that the moment I enter the Actual date against a Milestone it gets disabled, and you cannot change the date again?

I have problems where they enter an Actual date, and then they change the date again later on. The bussiness does not want this to happen.

Thanks.

Regards,

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member230675
Active Contributor
0 Kudos

Hi,

If you are using milestone on network activity then actual date will get copied from activity confirmation, in this case you can make the actual date on milestone as display field in OPUC.

Tnx.

Abdul

Former Member
0 Kudos

Hi,

Sometimes they do not confirm the activity, which means they just put in the Actual date without confirming. Is there something else that can trigger the Actual date and make it disabled after you enter it?

regards..