Plannning of WBS in ECP

Former Member
0 Kudos

Dear All,

We are using Easy Cost Planning. For that out of 5 WBS I want to do planning only for 2 WBS's. So I have set planning indicator for those 2 WBS only. But in Easy Cost Planning I can see all the 5 WBS's.

So how can I eliminate those extra WBS's ?

Thanks in advance

Girish Lashkar

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

In Planning profile (OPSB) tick planning elements