Hello,

we are trying to add Logical System in transaction SOLAR_PROJECT_ADMIN into the project on the System Landscape tab.

Problem:

Dropdown list shows the correct clients but the "Enter" pushbutton is grayed out and none of the clients are able to be selected.

I suppose we are missing some configuration somewhere..however RFC connection is working in SM59 for Connection Test and Remote Logon between Solman and satellite system.

Any tips to check from configuration or elsewhere?

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi

did you assighed the system role for the logical componet on the system tab of SOLAR_PROJECT_ADMIN, please use the button "system role assignment" and try. But this should be same as the sytem role assignment in SMSY. please verify

here the Blog for verification of your SOLAR_PROJECT_ADMIN config

[/people/sapna.modi/blog/2007/09/17/sap-solution-manager-40--project-preparation-phase-part-ii|/people/sapna.modi/blog/2007/09/17/sap-solution-manager-40--project-preparation-phase-part-ii]

And help link[add logical comp to project|http://help.sap.com/saphelp_sm70ehp1_sp23/helpdata/en/dc/cd7c0545724a30ab22f54d24a3bf3e/content.htm]

and it can be an authoraisation issue, check the user has needed authoraisation, (here SAP_SOL_PM_COMP or SAP_SOL_PROJ_ADMIN_ALL )

checkk here [roles in solman|http://help.sap.com/saphelp_sm32/helpdata/en/45/cb27429d16db2ce10000000a1550b0/content.htm]

Jansi

Paul_Babier
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Kuki,

Just a question, these logical components that you are trying to select in SOLAR_PROJECT_ADMIN.... have they already been created in SMSY? Normally I would assume they have been, but you didn't mention you created them in SMSY and can't add them in SOLAR_PROJECT_ADMIN. Perhaps this is what you may have overlooked in the configuration?

Additionalsl you would want to review SAP Note 907768 - General note for Change Request Management ST 400

and ensure you have applied all the required Notes for your SP level.

Regards,

Paul

former_member212731
Participant
0 Kudos

Yes, thanks!!

The logical component was not completely created in the System Assignments in SMSY. The configuration was completed and the problem was resolved.

Thanks for the help!