on 02-18-2011 10:39 AM
Dear All,
My client uses network cost planning and option determine planned cost after release. Now client decided to use Result Analysis (RA) and want to use Unit Cost Planning (UCP).
Now, problem is RA (KKA2) considered already planned network cost for running project. So that we cannot use UCP in loading full cost of any running project.
Please, suggest any way to avoide network planned cost in RA.
Regards,
Nilesh.
In RA configuration you can assign which costs to select using line ID's - here you can use value category to seperate the UCP.
You will have to use a different set of cost element to plan UC
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Virendra and All,
Thanks, Virendra for your useful answer.
I want to share another two options to check its possible effects, they are as as follows:
1) Remove costing variant from network and activate option do not dtermine plan cost.
2) Use any suitable RA userexist for selecting plan cost in RA (From suitable source).
Request, your opinions on above two options and any other effective option from your side.
Regards,
Nilesh.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.