cancel
Showing results for 
Search instead for 
Did you mean: 

Ignore already planned network cost in RA

Former Member
0 Kudos

Dear All,

My client uses network cost planning and option determine planned cost after release. Now client decided to use Result Analysis (RA) and want to use Unit Cost Planning (UCP).

Now, problem is RA (KKA2) considered already planned network cost for running project. So that we cannot use UCP in loading full cost of any running project.

Please, suggest any way to avoide network planned cost in RA.

Regards,

Nilesh.

Accepted Solutions (0)

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

In RA configuration you can assign which costs to select using line ID's - here you can use value category to seperate the UCP.

You will have to use a different set of cost element to plan UC

Former Member
0 Kudos

Dear Virendra and All,

Thanks, Virendra for your useful answer.

I want to share another two options to check its possible effects, they are as as follows:

1) Remove costing variant from network and activate option do not dtermine plan cost.

2) Use any suitable RA userexist for selecting plan cost in RA (From suitable source).

Request, your opinions on above two options and any other effective option from your side.

Regards,

Nilesh.

virendra_pal
Active Contributor
0 Kudos

Option 1 is easier

Former Member
0 Kudos

In addition to the above posts you can check user exit KKAG0005 to include a code that will satisfy your requirement.

Regards,

Gokul

former_member230675
Active Contributor
0 Kudos

Hi,

You can also make changes in OPSV settings.

Tnx.

Abdul