on 02-18-2011 10:04 AM
Hello Everyone,
Here I am planning to use strategy group 50 for the finished product. I have given PIR Qtys for the same and when MRP is run system is automatically raising planned orders of order type LA. Which means the same can be converted to production order and I am able to convert the same.
But as I understand with strategy group 50, you can convert planned orders to production orders only if sales orders exist and
Dependent requirements for lower levels are thrown and can be manufactured but not header material.
So I am not sure why this is happening. Or is strategy group 50 not supported for AFS.
Please do provide inputs.
Sincerely,
Aji Kurian Mani
Hello Aji Kurian Mani ,
Currently, AFS is designed to support only strategy group 40.
Thanks and best regards,
Deepthi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.