on 02-18-2011 9:38 AM
I want to config following scenerio.
The objective to create the config to have provision for outward freight.
While depatching the material i want to give some amount of provisional freight, at time of PGI the a/c forfreight should be
Freight A/c Dr 100
To outward freight clearing a/c 100
now once we receive the freight bill from transporte, the a/c entries for IV should be
Outward freight clearing Dr. 100
Freight Dr 10
To Vendor 110.
Regards,
Pranav dave
this kind of scenario is implemented in SAP standard using the shipment in the transportation module.
have a look at this documentation:
http://help.sap.com/saphelp_erp60_sp/helpdata/en/93/74409f546011d1a7020000e829fd11/frameset.htm
The scenario is available since 4.6c release
regards
Roberto
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.