MTO -

Former Member
0 Kudos

hello all

In MTO process we created sales order , with referance to SO the purcase order is created, in po there are 5 line items, problem is for the 2 line items in the po acoount assignement have been maintained but for the rest of the 3 line items in the po the account assignement is not maintained. any one can through some light on this issue

thanks in advance.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

ok

madlercm
Active Contributor
0 Kudos

If you use MRP to create the PR, check "Ind/coll" indicator in MRP 4 View. For SO account assignment it should not be "2".