on 02-15-2011 11:58 AM
Dear All,
Can we have any table or trasaction to get WBS element budget data on monthly wise.
Thanks in advance.
Thanks
Konda Reddy
Konda,
You have only Overall and Annual Budget for WBS.If you want to control monthly, you can release the budget monthly or quaterly (CJ32) from annual budget.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
Pl try table RPSCO with value type 41, This will give budget date
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi, no you cant.
You can do it only deriving FM account assignment, and run report for them
Edited by: alex ice on Feb 15, 2011 1:39 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.