Former Member
0 Kudos

Hi all, I am applying dunning via emigall.

Just wondering can we migrate two dunning records with different levels on a same issue date with same dunning procedure? If yes, can we apply 3rd dunning record with same issue date as previous but with different dunning procedure?

Please note all three dunning levels are for the same account.

Any help/input would be appreciated.

Regards,

Akif

Edited by: Akif77 on Feb 15, 2011 7:23 AM

1 REPLY 1

AmlanBanerjee
Active Contributor
0 Kudos

Hi,

Please refer to the SAP note 1497366.

There has been a SAP program correction which has been done through this note, in which now it is now sorting the FKKMAZE entries by latest Issue date (AUSDT) and dunning level (MAHNS)

Previously, it was sorting the FKKMAZE entries on the basis of latest issue date (AUSDT) and Laufd (Date).

May be the application of this note would help you in resolving your problem...

Hope it helps....

Thanks,

Amlan