Dear Sappers,
I've a forecast for 100 quantities which is available in MD04.
If I receive delivery order for 80 quantities, in MD04 I get the requirement as 80 against delivery order and 20 against forecast.
My requirement is to cancel forecast quantities in MD04 once I receive the delivery order.
Thanks
PKB
Hi,
I'm not sure what you mean by forecast; is it PIR? or material forecast.
If you say that sales orders consume "forecast", my guess is that you mean PIR, with a planning strategy like 40.
In case of PIR, you can use a standard transaction to delete unconsumed planning -- MD74.