BOM selection in Subcontracting PO

Dear Guru's,

We are using subcontracting Purchase Orders. For one material we are having more than one BOM. We want to select either of them while exploding BOM in purchase order. Please suggest the settings

Regards,

SAP CONS

Former Member
Former Member replied

I have a similiar situation and I do it in this way.

1. Maintain two production versions, one for each BOM you have

2. Assign the default production version to the subcontracting info record

3. When you create subcon PO, the default production version is used. If you want to change it, go in the item level "Material Data" Tab, click "Re-explode" and choose the production version you want

Maybe there's some better way around, but that's the way I used. Hope it helps.