on 02-14-2011 5:59 AM
Hi Experts,
We use SRM 7.0, ECS scenario.
Is that possible to add a new item with reference to SC in contract maintanence screen? Just like adding a new item 'from an old sc' in PO maintanenc screen.
Is there any configuration related about it? Or is it related with patch levels?
Many thanks.
Hi,
There is Add Items -> Add items from SC in Contract.
I think no configuration is required.
Regards,
Masa