on 02-11-2011 2:25 PM
Hi,
We are running on SRM 7.0 & ECC 6.0(Ehp 3). Will this work? As in will the P2P scenario work? Basic shopping cart creation - PO - GR - IV?
Is it mandatory to have Ehp 4?
Regards
Edited by: sivakumar lakshminarayanan on Feb 11, 2011 3:26 PM
Procure to Pay is addressed in the release note for ECC 6 EHP 3. So I believe it is supported there.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
SRM 7.0 supports backend connection from R/3 4.7 to the latest.
New functions like service hierarchy handling work with only EhP4.
Regards,
Masa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
It depends on your current scope and which new function are you going to use.
You need to maintain "Define System Landscape" customize when backend system is changed.
If you are classic mode, please note PO creation is via ESOA with EhP4 for supporting service hierarchy.
Release note help you to check new functions.
http://service.sap.com/releasenotes
Regards,
Masa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.