on 02-11-2011 2:43 PM
Hi
we would like to extend the setup matrix use for the halb products now, currently we use the setup matrix for the fert products and it works fine. our fert = halb+packing, when extending the setup matrix use to the halb products what changes need to be done.
do we have to create a new setup matrix for the halbs or..can you pls share your ideas..
Hi, its advisable to create a new setup matrix for the halb product.
Ensure all the w.c on which setup sequencing is to be done are single mixed resource.
Assign the newly created setup matrix to single mixed resource
In the routing assign the setup group
Re transfer your PDS
create a test planned order in APO rrp3 and test if the setup group is arriving or not
You ca use the existing sequencing heuristics
Regards
Amlan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.