on 02-11-2011 11:00 AM
Hi All,
Greetings!!!
A query, regarding ETO (Project system)
ETO scenario, For production, reservation will be create through WBS element. After production , If I do delivery and PGI, production order reservation is not deleting.
Same material If I do delivery(LP) through CNS0, then order reservation is going to delete after PGI. But Sales order price is not copying to Billing If I follow this process.
Is there any copy controls to flow the sales price to billing when delivery happens through CNS0. If not
Which requirement class and movement type I need to determine in Sales order.
Please do needful.
Very High,
Thanks,
Prasad.
This is standard SAP
SAP process is to deliver project stock using project delivery , where in PGI happens against the reservation created & deletes RESERVATION.
wherein if you do PGI for order ( sale order or prod order ) , it happens against project stock ( spe stk Q - 281 movement ) i.e., against WBS element
I faced the same for sale order delivery of project stock .
we are selecting FINAL Issue indicator through user exit which triggers when PGI is clicked
This will delete RESERVATION from stock overview
hope this helps ...Let me know if you found any alternative
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.