on 02-11-2011 7:38 AM
Dear all,
We want to begin using the INPUT PROCEDURE addin in our QM module, we already have customized this addin but now we are facing a master data issue, that is, when we update the inspection characteristics master data, the actual inspection plans do not take this changes into account.
My first question is: Is there any way to force the actual inspection plans to be updated with the actual inspections characteristics parameters ?
In particular, we want to force the option 'Input processing' in the control indicator, and the Input processing value in the Quant. Data.
Alternatively, is there any way to mass update this informations directly at inspection plan-characteristic level ?
Thanks in advance.
what i understood is u are doing some changes in MIC and u want those changes to be updated in inspection plan.
for this go to spro -qm - client level settings - tick 'Replace master insp. characteristics'
whenever u do changes in mic and save , system will show list of inspection plan in whcih this mic is used, u can select those and do mass changes
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.