on 02-11-2011 6:56 AM
I am executing the automatic allocation scenario where I have to create a purchasing list using OAPC ( TA: WRFAPC01) when I assign material and I try to release the purchasing list .I get the erroru201D No scheduling has been performed for itemu201D kindly let me know how can I correct this issue .
Hi,
You can check whether the stock is available for the particular material.
If required quantity is not available then need you to add stock for that material...
Regards,
Sudha .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.