Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

WBS Dates not updated from confirmed activities below

Dear All,

Require your help on this.

I have a Project Definition where we have Multiple WBS (upto level 2) and we are using single network.

Activities are distributed in various WBS levels (Lowest WBS).

For example I have WBS where there are three activities, and two activities have status CNF, and one activity has status PCNF (Partially confirmed)

When I re-schedule the project the Early start date of the Partially confirmed activity is getting transferred.

Ideally the Early start / Actual start of the CNF activity should be transferred to the WBS level.

Due to this when I "determine actual dates" @ WBS level, it gets over written after scheduling.

For WBS I Re-schedule using Top Down ; Forward in time ; WBS determines dates

For Network I Re-schedule using Strict bottom up ; Backward in Time ; Network Determines Dates

I have ticked Adjust Basic dates & Start in PAst 999 ; but still the Actual start dates of confirmed activities are not transferred.

Please help me

Former Member
Not what you were looking for? View more on this topic or Ask a question