Hi,
My Project's WBS contains external activities assigned to it and those activities have some quantities with them (defined in activities quantity).
When i create quotation from dp81, all quantities which are maintained as internal activities are picked up based on activity type, however quantities which are maintained for external activities are not picked up. one important this is that the amount for these external activities are appearing as per expected in dp81.
I have checked and verified the configuration of DIP Profile, but cannot find the solution. any idea on picking up external activities in dp81?
Thanks
Edited by: Measum Kumail on Feb 10, 2011 9:12 AM
hi, following are the characteristics in my dip profile.
activity number: Ch rlvnt,
acitivity type: ch rlvnt
cost center: ch rlvnt
cost element: ch rlvnt
material: ch rlvnt, mat det.
obj #: ch rlvnt, struct
trans curr: ch rlvnt, no summ
uom: ch rlvnt, no summ
Sources: 0021 Planned Costs - Total Records 100%
Mat Determination: Material is S-1301, Transfer Quantity & costs
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi, following are the characteristics in my dip profile.
activity number: Ch rlvnt,
acitivity type: ch rlvnt
cost center: ch rlvnt
cost element: ch rlvnt
material: ch rlvnt, mat det.
obj #: ch rlvnt, struct
trans curr: ch rlvnt, no summ
uom: ch rlvnt, no summ
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for your reply, but i dont have the problem w.r.t. to cost. costs for external activities are appearing in dp81, but my problem is for quantities (activity quantity).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
"Activity Type" & "Internal / External Activity" are both different.
You might have maintained "Activity Type" as one of the characteristics for your sources in DIP Profile.
When you maintained "Internal Activity" & assinged a workcenter, the "Activity Type" (maintained in the workcenter in Costing tab or which you selected using F4 option in the Project) ....... is responsible for cost updation & is subsequently proposed in your DP81.
Use "Cost Element" as your characterisitc & then try some cost updation for your external activities with reference to this CE.
regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.