Iu2019m having difficulty finding a method to settle from a work order to a cost center with line item detail. When an order is settled with KO88 or KO8G the total value for that work order/cost element combination is combined and posted to the cost center as a lump sum with the description of CTR\######. Users would like to see the individual values that posted to the work order in a cost center report such as KSB1.

I donu2019t see anything in the settlement rule, settlement profile or allocation structure that will allow line item settlement from work order to cost center. Is line item settlement possible when settling to a cost center? Is there an alternate way to see these expenses as line items in KSB1?

Thanks,

Jeff

replied

Hi Jeff

Thats standard design... "Settle by Cost element" means settle the total amount for each Cost element..

You will get 1000 $, but not individual line items... Individual Line items are only possible for Internal Orders with Investment measures (AUC)

BR,Ajay M