Budget Entry

former_member599430
Participant
0 Kudos

Dear guru,

while i am using t.code FMBBC i am getting run time error and i did debuging the error is mention below

For FM area the direct way (L_F_TABLEAREA-FIKRS = U_FM_AREA) is not

used here as table group FMBD only enabled if component EA-PS is

active, if it's not active the direct way would lead to syntax errors

if the function group FMBD_DATABASE_ACCESS would nevertheless be

loaded somewhere.

i need some solution.

Thanks & Regards

Soraj

Edited by: soraj kumar on Feb 8, 2011 11:34 AM

1 ACCEPTED SOLUTION

iklovski
Active Contributor
0 Kudos

Hi,

Check in SFW5 if EA-PS is switched.

Regards,

Eli

View solution in original post

7 REPLIES 7

iklovski
Active Contributor
0 Kudos

Hi,

Check in SFW5 if EA-PS is switched.

Regards,

Eli

former_member599430
Participant
0 Kudos

yes i checked EA-PS is switched on i dont have any idea about SFW5 and EA-PS so what i have to do please let me know

Thanks

Soraj

0 Kudos

What SAP release do you work with?

former_member599430
Participant
0 Kudos

We are using ECC 6

former_member599430
Participant
0 Kudos

still i am unable to posting the budget in FMBBC.

former_member599430
Participant
0 Kudos

Dear guru,

I found that in table GLU1 field RFIKRS is missing becoz of that i am getting error. can any body give me soultion how i will make the setting so that error will be closed.

0 Kudos

Hi,

GLU1 is a structure.

Try to run report RGZZGLUX