on 02-07-2011 11:01 AM
Hi
I have populated with value of budget in IM32 in Investment Management for year 2011. Now, I am trying to supplement the budget to couple of measures assigned to an investment program. But, the systeme is displaying the error message: "Annual Budget 2010 is less than distributed budget". Actually, these measures (projects) are assigned to investment program in 2010 and now I would like to draw the budget and distribute it.
Is there anything missing in the process and how to avoid the error message and post the budget successfully.
Thanks and regards,
Basav
Hi.
Be aware that year in Selection screen in tcodes IM52, IM30 etc is not 'year of budget distribution, supplement etc'.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
It seems you are distributing budget to the measures more than what is available / planned in the program. System wont allow this.
If you are doing annual budgeting in program then distribution to the measures also should be annual.
Tnx.
Abdul.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
check your budget value for the 2010 and also how much you want to distribute.
IM52 is the transaction where you distribute the budget to the project Definition.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Below is the IM32 values for the 2010 Inv program
Per Bud Tr Curr Cur Bud Distr Distributable Plnd total Carry forward
Overall 40,544.36 USD 40,544.36 38,046.00 2,498.36 0.00 3,160,270.16
2005 USD
2006 USD
2007 USD
2008 USD
2009 25,398.36 USD 25,398.36 0.00 25,398.36 0.00 40,148.71
2010 15,146.00 USD 15,146.00 0.00 15,146.00 0.00 2,895,601.45
2011 16,450.00 USD 0.00 0.00 0.00 0.00 0.00
2012 16,450.00- USD 0.00 0.00 0.00 0.00 0.00
When I carry out the distribute budget for projects thru IM52, it is giving the error. Is there anything missing?
Thanks,
Basav
Hi
Thanks for your feedback.
I have also budgeted to 2011 (annual) for an amount $270000.00 and trying to distribute with IM52 for one of the project for an amount 16000.00 only. But, it is giving the error "Annual budget 2010 less than distributed budget. The error is for the year 2010.
The budget has been carried forward from year 2009 to 2010.
Regards,
Basav
User | Count |
---|---|
91 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.