on 02-05-2011 8:21 PM
We had to change a customer number and had to create new sales Contract and cancel old one contract with old customer number. The new sales contract will continue to refernce the Project used for older contract.
Is there any impact on the project? or anything else to consider from project perspective?
Thanks
Hi,
If you are using RA then consider how you are doing the revenue planning.
If it is automatic planning from sales order then it may impact otherwise it wont (if you are planning revenue on WBS element directly)
Tnx.
Abdul