Dear Experts,

can we assign progress version to WBS and Activties in mass chage?

Actually problem is that we want to assign progress version to each and every WBS and Activity.

We want progress reports which are not possible w/o progress version.

Is this possible?

please reply

Accepted Solutions (1)

Accepted Solutions (1)

former_member230675
Active Contributor
0 Kudos

Hi,

Please try some BADI.

Standard it is not possible.

Tnx.

Abdul

Answers (2)

Answers (2)

virendra_pal
Active Contributor
0 Kudos

have you checked substitution rule?

Former Member
0 Kudos

yep..tried out but progress version is not there

kalpesh_agrawal
Participant
0 Kudos

Hi,

Try mass changes by CNMASS

Former Member
0 Kudos