on 02-05-2011 11:13 AM
Dear Experts,
can we assign progress version to WBS and Activties in mass chage?
Actually problem is that we want to assign progress version to each and every WBS and Activity.
We want progress reports which are not possible w/o progress version.
Is this possible?
please reply
Hi,
Please try some BADI.
Standard it is not possible.
Tnx.
Abdul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
have you checked substitution rule?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Try mass changes by CNMASS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.