Discrete opt lot size

Former Member
0 Kudos

Dear experts ,

I am executing discrete optimization but it is not taking lot size and rounding value into account. On SNP PDS i am using minimum lot size 1 but on product master i am using 200 and rounding 20 , but optimizer is creating planned order with 180 pc. ..... Someone can help me please.

Regards Mauricio

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

A couple of quick checks:

Have you activated the control of lot size constraints on the "General Constraints" tab page in the SNP optimizer profile?

Is the value for the plan explosion set to 5 Production Data Structure Generated from R/3 in the location product master (tab page PP/DS) in SAP SCM?

regards

Ian

Former Member
0 Kudos

Hi lan ,

Yes on master data the value is 5 and on general tab i am using Maximun PDS Lot Size and on discrete constraint i am maintaining days for minimun PDS lot size and integral PDS.

In product master data i am using Lot-for-lot . But still not working.

Please help me with this issue.

Thanks in Advance

Mauricio

thamizhchelvan_gunasekara
Active Participant
0 Kudos

Hi ,

Optimizer will not consider rounding value nor rounding profile , if you want to use rounding values based lot size use cost profile in PPM.

Thanks and regards

Thamizh

Former Member
0 Kudos

Dears ...

The issue is solved ..... it was a missing flag. I had to maintain discretization field at PDS and Lot for Lot at material master.

Regards

Mauricio