on 02-03-2011 12:19 PM
Hello All,
Would you be able to do a check for me on whether this is expected behaviour:
1. Create WO
2. Release WO (auto sched flag will be ticked)
3. Take the flag off, change basic start dates
(here your basic start and finish & sched start and finish dates will
be different)
4. Next save the work order
5. Go back to the WO and notice that the dates are still different
(working as expected so far)
6. Now, add a component & Save
PROBLEM: (sched dates change - no auto sched flag ticked, WO is also
already released, so auto sched does not get auto ticked here)
Do you experience the same behaviour?
Regards,
Mantas
If they not ticked you have to backflush them separately
Edited by: nitin_rjit1984 on Feb 8, 2011 11:02 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.