CTS+ - error in deployment Pi 7.11

Former Member
0 Kudos

Dear Gurus.

Import fails with error:

comsap.aii.ibtransportclient.Xitransportexception "

Import failed because of fusiness system transfer: According to information in SLD, the object reciever agreement FILE2IDOC ERD_200 ZHR_FRAMES to be imported must be mapped to reciever agreements FILE2IDOC ERQ_350 ZH_FRAMES. this would owervrite an object also to be imported caused by com.sap.aii.ib.core.transport.api.PostprocessingException.

Whats wrong?

Regards

Vladimir

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Did you assign the transport target groups in the SLD of both the system?

Like Your QA1 should should be added as the target group in the Dev business system.

Regards,

Vamshi.

Former Member
0 Kudos

Yes

The target of ERD_220 is ERQ_250.

Regards

Former Member
0 Kudos

Hi

the object reciever agreement FILE2IDOC ERD_200 ZHR_FRAMES to be imported must be mapped to reciever agreements

FILE2IDOC ERQ_350 ZH_FRAMES

You should map the target system to client 350 not to 250. i.e ERD_220 to ERQ_350.

Regards,