Error: Source not included in list despite source list requirement

former_member562193
Participant
0 Kudos

I have maintained the Source list in ME01 for the Material/Vendor combination, however I still receiving an error "Source not included in list despite source list requirement" while creating PO for the same Material/Vendor. Can some one tell why?

Regards.

Accepted Solutions (0)

Answers (2)

Answers (2)

JL23
Active Contributor
0 Kudos

what valid from date did you enter?

is the requisition older than this valid from date?

do you reference a contract, if so, you have to add the contract as source in ME01.

former_member562193
Participant
0 Kudos

Valid from and To dates are correct in Source list.

I tried creating PO for a different Plant and I was able to crete the PO successfully without getting this error message. However, for Plant 1000 this error is appearing. The indicator for Source List Requirement at Plant Level is also not checked for any of these 2 plants (though it does not matter if the source list is maintained). Something wierd!

PO date is within the Source list date range and No Contract reference is being used in the Source List and PO.

Edited by: Lucky on Feb 3, 2011 5:39 PM

JL23
Active Contributor
0 Kudos

the source list is plant specific.

the requirement can either be set in customizing in general or in a material master individual.

you say:

Valid from and To dates are correct

PO date is within the Source list date range

How do you think can we check if this is true. Nobody here has a glass bowl, we can only help based on infos you give us.

Give the dates (valid from, valid to, PR creation date, PO creation date, delivery date) as example, then the community can tell you whether the dates are correct or not.

SAP would not complaign if everything is correct.

Former Member
0 Kudos

Hi

Have u checked the source list in the Material Master.

Regards

JK

Former Member
0 Kudos

create source list for the material and vendor combination in the plant 1000

former_member562193
Participant
0 Kudos

Valid From Date - 01.01.2011

Valid To Date - 31.12.2011

PO Date - 03.02.2011

Delivery Date - 10.02.2011

Purch Org - 1000 (In Source List and PO)

Source list maintained with above dates for both the Plants.

Not using PR. Creating PO directly (i.e. without PR reference) using the same Material and Vendor as in Source list.

JL23
Active Contributor
0 Kudos

is your source blocked?

do you have an info record?

Former Member
0 Kudos

Please check the valid from and valid to in source list.

It is possible that the vendor may not be valid as on date.

Thanks & Regards,