on 02-03-2011 5:34 AM
Have looked into the transaction V_R2 and with this transaction we see how many orders and can evaluate the order stock for a special material. V_V2 is used to make the real replanning and it seems that this can only be used for orders not yet confirmed. Is there any transaction or is it possible with this 2 transaction to also get a replanning for orders already confirmed or is it only CO06 that can be used for replanning the orderstock for a certain material.
Motive behind the question:
The shortage of material for the moment is a big problem but sometimes it happens that the supplier has been able to supply us with shorter delivery time even though the purchase order is confirmed with longer leadtime. Our orderplanners want to have a tool to make replanning for all orders with a certain material and it should be easy to update the confirmation for these orders.
In CO06 they have to manually update order for order.
Do you have any solution for our problems ?
I think that with V_V2 you can re-plan all orders; perhaps the only limitation being if you work with the indicator "fixed date" ON.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.