Hello,

Is it possible to create delivery(with or without reference to sales order) for milestone billing plan. And bill the complete value of the material.

Exception:-The delivery should not be through CNS0

Edited by: Aadesh Kamat on Feb 3, 2011 6:22 AM

Accepted Solutions (1)

Accepted Solutions (1)

former_member183879
Active Contributor
0 Kudos

If the project is enabled with a network and milestones which are enabled for billing function, then it is not possible to create such deliveries from VL01N, you only have to use CNS0

0 Kudos

Hello,

Thanks for the reply.

The billing plan is a plain billing plan, w.r.t item category in the sales order, it is not related to network or project milestone. Can the delivery be done through VL01N in this case?

former_member183879
Active Contributor
0 Kudos

Hi,

If it is milestone billing, it should be linked to either a project or a WBS element atleast. There is no way by which you can have a milestone billing plan in your sales document without a network/WBS/Project.

If I am not correct, pls lemme know and explain your process.