Wrong week in next number maintenance

Former Member
0 Kudos

Hi,

When going into next number maintenance and entering a prefix for year and week like

%DATE_TIME.[yyww]%

I get the sample 1106 even though the week in sweden is 05 at the moment.

My servers that are running Windows 2003 were first having United States as the regional settins,

but even though I have changed them to Swedish regional settings and restarted the wrong week

is still showing.

Are there some other setting in SAP ME that affects the settings for the calendar?

Br,

Johan

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

Hello Johan,

Please refer to SAP Note #1485211 to clarify this behavior.

Regards,

Alex.