Hi,
I am creating PO from ME21N and asigning WBS as account assignment. I can see this PO value as commitment in cost element report S_ALR_87013542 but I see this value in Assigned orders in budget report S_ALR_87013558. I don't have any issue from availability control but why I am not seeing this cost against committment.
Hi,
Is this standard behavior when I won't create PO from PS directly(PR-->PO).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
No this is not a standard behaviour.Can you chcek the cost element against which the commitment is reflected in S_ALR_87013542.Also do an analysis(Extras --> Availabity Contril --> Analysis) in CJ30/CJ31.So that you can identify, against which cost element is this PO value reflecting and its corresponding value type and business transaction.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.