Error Message : Budget exceeded for WBS(BP604)

Former Member
0 Kudos

Hi

Im getting a message when im trying to post a commitment to a WBS through PO.

Originally for the WBS element USD-110107117 I pushed down $15K and yesterday I was told to push down another $40k. Bringing the total to $55K.

Today I'm trying to cut a PO (73910) for an amount over $15k and it says that the budget exceeds. But if I cut it below or equal to $15k it works.

But if you check the Budget it's right there are $55k.

Can you please help me why still im getting this message.

Your advice is appreciated.

Thanks and Regards

Megha

Accepted Solutions (1)

Accepted Solutions (1)

Makal
Active Contributor
0 Kudos

Hello Megha,

Execute the report "S_ALR_87013558 - Budget/Actual/Commitment/Rem Plan/Assigned " & check what is the available budget. This should help you.

Regards,

Amaresh Makal

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi

Thanks for the reply.

The budget available is 0. This 55000$ is assigned to the top level WBS USD-110107117.

I tried distributing this to lower level by using CJ32 but still it doesnt work.

Any suggestions.

Thanks and Regards

Megha

Former Member
0 Kudos

Dear Megha,

"Budget distribution" or "Budget Allocation to lower level WBSEs" both are CJ30 only.

CJ32 is to release some part of the budget against a WBSE, which is primarily allocated in CJ30 only.

go to CJ30 & enter your required budget for the WBSE.

regards

Makal
Active Contributor
0 Kudos

Dear Megha,

Budget distribution should be done from the CJ30. CJ32 is for release.

Regards,

Amaresh Makal

Former Member
0 Kudos

Hi

Thanks for this.

Another question is that this 55000$ is allocated at level 2 WBS USD-110107117. In this assigned amount is 15000$.

Project is USD-110100000

The WBS element which im assigning in the PO is at level 4 USD-110107117-B-5656-03 which of now has 0 value.

So how do i bring down this value of 55K to this level USD-110107117-B-5656-03 .

Also if i give any amount less that 15000$ it is taking.

This sounds strange.

Any help would be highly appreciated.

Thannks and Regards

Megha

Makal
Active Contributor
0 Kudos

Hi Megha,

So how do i bring down this value of 55K to this level USD-110107117-B-5656-03 .

Also if i give any amount less that 15000$ it is taking.

This sounds strange

System is behaving normally. You need to understand the bsics. If you ask specific questions, then it can be answered.

I suggest you to first study/ get yourself trainned on costing & budgeting in SAP PS.

Best Regards,

Amaresh Makal

Former Member
0 Kudos

Hi, may be budget were changed(reduced)?

Former Member
0 Kudos

HI,

What is the available budget on the WBSE?

regards