Dear All,

We are implementing ECC 6 in one of our client.

Our client manufacturer of x finished product, they want monitor the production process through Project system and deliver should be through project system,

We did the complete configuration from Production order till delivery in PS is working fine.

But when we try to post billing document from the delivery document, the system is showing the following error,

Document is not relevant for billing: LP is not relevant for F2.

Our doubt is in this process, whether excise invoice will be generated or not?

this LP is hard coded in SAP, We are unable to rectify the error,

our GO-LIVE date is 1st March

can any one help us to solve this issue?

Thanks in advance

regards

Elango

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

thanks to all....issue is resolved

Former Member
0 Kudos

Hi, sapelango ,

Would you please tell me how you resolve the issue?

I encounter the same problem when I try to create a billing document with reference to the delivery note created with TCODE CNS0.

Thanks in advance.

regards.

Cherry

Former Member
0 Kudos

HI

Please check the controls for Item cateogrie wether it is relevant for billing in Billing Relevance field.

Regards

Santosh.A.R

Lakshmipathi
Active Contributor
0 Kudos
LP is not relevant for F2

What is LP ?? Is it Delivery type or Item Category ?? Nevertheless, copy control is missing in VTFL.

whether excise invoice will be generated or not?

If physical material movement is there from a manufacturing plant to outside, then definitely, you should generate an excise invoice

thanks

G. Lakshmipathi

Former Member
0 Kudos

HI

Thanks for your immediate reponse

LP is delivery type,

we are doing CNS0 t.code to do the delivery and VL02N t.code PGI is done,

But when we do billing the system is showing that error

Regards

Elango