Program CN4 / CN41N does not give info for the fields in table PROJ for Finish date, Forecast start and forecast finish.

Any means fof getting these field values or any specific report?

Warm regards

ramSiva

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

RamSiva,

As mentioned CN41 & CN41N is not providing the forecast dates of project definition.But PROJ table has these fields.

Even CJ24 is not displaying the forecast dates of project definition, but I am able to view the forecast dates of Project definition in display forecast Old/New dates option of CJ29.

Edited by: ravi kumhar on Feb 2, 2011 7:07 AM

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

I did find the Forecast dates in CN41

Its Finish (F) and Start (F). You can choose these from the layout.

BR

Anjali

Former Member
0 Kudos

Hi Anjali

I have seen this fields but i did not find them updated. (They are blank even though having data)

If you get data, please let me know which PS info profile u have used,

Thanks and Warm regards