Transfer Gloabal Settings - in SCM Prod from ECC Prod

Former Member
0 Kudos

I want to transfer the new Fiscal year variant from ECC Prod to SCM 7.0 Prod. I was able to do this in SCM Dev & QA boxes as Source system for ECC was defined in both systems. However ECC Prod source system is not defined in SCM 7.0 Prod system & BASIS is not willing to open the box and define ECC Prod source system due to some landscape restrictions. Ofcourse they will do in case of no other option.

I understand transporting the table entries is one solution, but i dont want that way as i have already updated the table records in Dev & QA and it will involve lot of manual work.

Just wanted to check if defining the ECC Prod source in SCM Prod is the preferred/standard way or not for transferring Gloabl settings?

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Tejinderg,

Yes, this is standard.

Best Regards,

DB49