Does MM-SUS Plan driven scenario support Services confirmation?

Former Member
0 Kudos

Hi SRM Gurus,

I need your input on the below scenarios.

We are considering MM-SUS plan driven procurement scenario for ECC-EHP4 and SRM7.0 EHP1 sys environment.

We also create service POs (D) with text type (non-service master) in ECC and need to send those to SUS.

I have below qestions.

1. Can ECC send service POs to SUS?

2. Can supplier do Order Acknowledgement (PO response) for those service POs in SUS?

3. Can supplier enter services confirmation for services performed in SUS to create service entry sheet (SES) in ECC?

4. Then, when SES is accpeted in ECC, will it update service confirmations in SUS for suppier to raise invoice in SUS?

Please provide your input for above qestoins for plan driven scenario. Thanks for your hepl.

Chandra

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

That was helpful on 1 and 2. Thanks Nikhil for your quick response.

Chandra

Former Member
0 Kudos

Hi,

We have the same questions.

Doyou know if it is possible?

Thanks,

Ivá

Former Member
0 Kudos

Hi Evan,

It is possible to collaborate with the supplier for service procurement on MM SUS scenario.

Even, SRM 7.0 supports service procurement classic where most communication exchage happens between MM and SUS. I guess, you donot need any development effort as well.

Thanks and regards,

Ranjan

Former Member
0 Kudos

Hi Chandra,

The answer to your first 2 questions is Yes. I will get back to you on the 3rd and 4th question.

Regards,

Nikhil