Hello all

We use Extended classic.

In SRM in PO field PO response unclicked but PO in MM field (ECC) confirmation required is checked. so

Reminder acknoledgment is generated. what must be the reason?

Regards

Krupa

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

In your ECC system, check if the 'Acknowledgement required' indicator is checked for the vendor for which this PO was cut. This causes the issue you have mentioned.

Regards,

Nikhil

Edited by: Nikhil RGupta on Jan 31, 2011 6:18 PM

Former Member
0 Kudos

Hello Nikhil

I have already checked this in Vendor Master in ECC before bringing this issue to our forum. Any other cause?

Regards

Krupa

Former Member
0 Kudos

Hi krupa,

Has the PO being created with reference to a contract? Does the contract has the option 'Acknowledgement required' checked or unchecked?

Thanks and regards,

Ranjan

Former Member
0 Kudos

Hello Krupa,

Please check acknowledge ment check has been flagged in vendor master data.