Is it possible to create a quotation or a sales order that is assigned to a project that has 'no project stock' (PROJ-BESTA) in the project profile? We are using a non valuated material in the quotation but get the error message CN769 'Material valuation is different'. Project stock is not required, we do need the revenues and the billing plans from SD.
Hi,
Check your requirement class derived for the material.
In the "Account Assignment" sub tab of requirement class maintenance, see the Valuation field value (for special stock) maintained.
It should probably be "blank" or "A" for your scenario.
regards