on 01-31-2011 8:44 AM
Dear Experts,
My client has run CJ88 of WBS for Rs.200000/- & after that he has reversed it & again he has run CJ88 for same WBS.
In this process, when i am checking assign budget column in CJ30, its showing doubled of it that is Rs. 400000/- & original budget is Rs.500000/-.
Also if he is trying to create PR for same WBS system showing budget exceeded error.
I also checked CJI3 & CJI5 reports, its also showing actual amount only Rs.200000/- & no committments.
Then where this Rs.200000/- hasbeen booked against which document.
Please suggest.
Thanks & Regards,
Arvind Tirlotkar.
.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
check the cost element assignment for the cost element group in case of duplicate remove it
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.