Dear colleagues,

1. What is the process difference (or implications) between creating measures and keeping appropriation request AND creating measures and replacing AR with the measure?

2. Once AR is replaced with measure what is the point of setting further system statuses for AR like Release, TECO, Closed. They seem not to have any influence on the created measure.

Thank you.

Accepted Solutions (1)

Accepted Solutions (1)

former_member230675
Active Contributor
0 Kudos

Hi,

>

> >

> 1. What is the process difference (or implications) between creating measures and keeping appropriation request AND creating measures and replacing AR with the measure?

>

If you do not want to use AR for budget revision or supplement then better to use the option create measure and replace AR.

>

>

> 2. Once AR is replaced with measure what is the point of setting further system statuses for AR like Release, TECO, Closed. They seem not to have any influence on the created measure.

>

>

While Releasing AR only it will be replaced by measure. After that no need to do any other status change for AR.

Tnx.