Hi Gurus,
We currently have WM module in place for normal production process i.e. for Production order type PP01 for a particular plant and a warehouse number.
We want to replace the process from production order to Process order i.e. from order type PP01 to PI01. I was looking at the Customizing for Warehouse Management under Interfaces -> Define Production for PPPI.. I see only the difference is Production scheduling profile between PP and PPPI.
I tested the process by creating a process order but Transfer orders didnt get created. I believe some piece of configuration is missing which is related to Order type PI01.
Please advice on the above.
Your inputs are highly appreciated.
Thanks,
Quantum.
Hi
In LE>WM>Interfaces-->PP interfaces, pls check for below
1. make sure u have selected the indicator 'PP Interface for Warehouse'
2. makesure u have assigned your order type to production scedule profile
3. in production scedule profile, in transport tab, maintain WM Request as 'X or 1' as per your requirement.
Rgds
Ramesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.