Hello experts,

We are currently developing a new product using NWDI as version control (with DTR), as build management (CBS) and as release management (CMS). We developed until now one functionality of the product, let´s call it "A". Once we finished the functionality "A" we are now able to deploy it on customer´s side. At the same time we have an maintenance contract to fix bugs of this release, we are developing new functionalities ("B" and "C").

The SVN version control has "baselines" that basically creates two versions of same product, both can be modified and merged. Is there such funcionality on NWDI? Do we have to create another track to every new functionality of our product?

Thanks and best regards,

Gabriela Vasselai

Accepted Solutions (1)

Accepted Solutions (1)

shreyas_pandya
Contributor
0 Kudos

Dear Gabriela,

I believe the below mentioned blog may give you justified explanation for this question.

/people/marion.schlotte/blog/2006/03/30/best-practices-for-nwdi-track-design-for-ongoing-development

Regards,

Shreyas Pandya