on 01-27-2011 11:45 AM
Dear Gurus,
I'm new to HUM and Currently I'm working on HUM.I've created a material and a packaging material.I created a Purchasing document and taking inbound delivery for the Purchasing document and doing packing in inbound delivery.
I made the Putaway process for the material and doing MIGO respect to Inbound delivery.In MIGO system creates a delivery number when saving instead a material document on saving.
I don't the exact problem.System is not giving any error message in MIGO.
Can anyone share with me the thoughts on this issue?
Regards
PKB
Hi,
As per my understanding the MIGO transaction does not support the packed inbound deliveries.
you need to do GR with VL32N then it will works.
Hope it helps you.
rgds,
Kris.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I too had a similar issue.
I had the inbound delivery packed and TO was open.At this stahe I treid to do GR agaisnt Inbound delivery in MIGO. System created another Inbound Delivery ( since Sloc was HU managed).
So, you need to confirm TO in LT12 which means PGR is done or as suggested in the above post, do the GR in in VL32N after TO was confirmed
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Very starnge issue.
Are you sure a delivery was created? Did you check purchase order history? What can you see?
Which paramters did you use in MIGO? A01 (Goods Receipt)-R04 (Inbound Delivery?
did you check the whether there's goods movement in MB51???
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.