Delivery note cannot be done through PROMAN

Former Member
0 Kudos

Guys,

User made mistake by using CN25 instead of CNMM, when wanted to issue material xxx on project xxxx, he clicked on « Post Goods Issue ».

To cancel the good issue, transaction CN29 was used.

A New CN25 on material. It is available in unrestricted stock but not linked with project xxxx, so DN cannot be done in transaction CNMM.

So using Transfer Posting mb1b transaction, transfer was done to wbs element using 415 movement type.

but the material is visible in project stock but not shown in proman.

Thanks.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Are you sure the user used transaction CN25 to do that? CN25 is used for confirmation of the activity and CN29 to cancel the confirmation.

Try to reframe your question once again in a proper way and then post. Maybe you will get a better response.

Regards,

Gokul

Former Member
0 Kudos

User used CN25 for Goods movements. and CN29 to cancel the movements.

Transfer of material was done using mb1b transaction with 415 movement type, to move material from unretricted stock to project stock

material is visible against the wbs element but not in proman

Using proman for creating delivery note for component, it says "No data was selected with the selection criteria entered."