We are trying to bring in SA Confirmations from SNC to ECC.
I did implement the OSS note related to EDI messages and using ORDRSP.ORDERS05 for this.
I would appreciate if anyone could provide information on how the idocs were mapped in PI or any tips on that front.
Any detail on what Idoc segments were populated would really help.
K
Hi Kedar
Please refer this thread
As such there is no XML interface available from SNC to carry SA confirmation to backend.
As Nikhil suggested you can try ROC_out xml.
Then in PI map this XML interface ROC_out to ORDRSP.ORDERS05
and maintain inbound parameter,
ORDR_SUS-Process code for message type ORDRSP
Please refer the side effects mentioned in note 810340
In standard R/3 system due to a technical reason - "The database table EKES has a field ETENS in its key, which allows a maximum of 9999 entries.Scheduling agreements can have many confirmation lines (order acknowledgements and/or shipping notifications), especially in the automotive industry, so the risk for an overflow of EKES table is high.
For this reason, it was decided to not allow order acknowledgements for scheduling agreements via IDoc".
So there is restriction of data flow.
Best Regards
Vinod
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Vinod / Nikhil,
Ok, we mapped DSC_Out to ORDRSP.ORDERS05 and brought it in to ECC.
However we noticed that ECC expects the message to respond to all the schedule lines.
For example, For Release 1, we have 3 schedule lines for Qty 500 , 1200 and 250.
When I publish a confirmation of 500 only at one time, it gives an errors on the ECC side saying there is a quantity variance.
There is an OSS note 456127 which mentions that the Quantity Check on the ECC side needs to be removed.
Any thoughts on this?
Kedar
Hi Kedar
You want the system to treat order acknowledgments for scheduling agreement items in the same way it treats order acknowledgments for purchase orders, that is, that it creates order acknowledgments based on the schedule lines in the IDoc (E1EDP20 segments) if a confirmation control key exists for the item to be confirmed.
Now in SA me33l, item details (F2)
There are Underdel. Tol and Overdeliv. Tol. needs to be maintained under GR/IR control. This is QUANTITY_CHECK
for the SA item level
For example, For Release 1, and you have Target quantity for 10000
3 schedule lines for Qty 500 , 1200 and 250.
In order to accept the confirmation of 500 , suitable underdel tol needs to be set. (Which is 99.95).
This does not look good as the tolerance level is set @ item level and you have multiple Schedule Lines
Try to enhance for the function IDOC_INPUT_ORDRSP
EXIT_SAPLEINM_009 -> Customer enhancement for tolerance change
Bring the tolerace level w.r.t to schedule line level
Best Regards
Vinod
Hi Kedar
Will I need to enhance the SNC application as well to trigger the proxy in the new namespace?
In General Name space used is
Namespace : http://sap.com/xi/SCMBasis/Global
Software Component version : SNC 5.1
for the Interface Mapping: DeliveryScheduleConfirmation_DelconfDelfor01_01
But now you have your own interface mapping done is XI....whenever the xml triggers it will be available under the above name space,
I suggest you take a look at the following FM /SCA/BIF_DELSCHEDC_OUT.
Take help of any developer to suggest how to proceed further.
Best Regards
Vinod
Hi Vinod
We are trying to implement the User Exit on the inbound function module to process SA Confirmations using ORDRSP Idoc..
However, I noticed that the Idoc does not carry the Schedule Line Number. I checked the DSC_Out message from SNC and that too does not have the Schedule Line number.
Not sure how the user exit can be used to validate confirmation qty with tolerances at SL Line level.
Any ideas?
Kedar
Hi Kedar
DSC out contains item number, Please check the below structure in your DSCOUT xml
- <Item>
- <SchedulingAgreementReference>
<ID>5500000095</ID>
<ItemID>000010</ItemID>
</SchedulingAgreementReference>
- <Release>
<ID>2</ID>
Question is ORDERS05 IDOC type can carry this information in E1EDP20 segment but there is no field mapping to item ID or Release ID
Approach can be enhancing the idoc to fetch this field from DSC_out xml, but the question still remains
There is no release id availalbe in R/3 how to map this one??? as you want to maintain the tolerance @ release id level
Better approach is to find out how these individual releases for SA items are uniquely stored in the table ???
Then you can reference that
Best Regards
Vinod
Edited by: Vinod Kumar Pedapati on Feb 15, 2011 7:12 AM
Hi Kedar,
You can maintain under and over delivery tole. in confirmation control key
path:SPRO>Materials Management>Purchasing>Confirmations>Set Up Confirmation Control.
create new confirmation control key for SA in confirmation sequence for AB Order acknowledgment maintain under and over delivery tole.
Regards,
Nikhil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.